Foundation Level study guide

Entry Criteria vs Exit Criteria

Entry Criteria define the preconditions that must be met before a specific testing activity can begin. Exit Criteria define the conditions that must be achieved to officially declare that testing activity complete. In Agile, they align closely with Definition of Ready (DoR) and Definition of Done (DoD).

Practical example

Entry Criteria (DoR): The test environment is up and running, test data is available, and the developer has marked the code as "Ready for QA". Exit Criteria (DoD): 100% of planned tests executed, 0 critical defects remain open, and 80% statement coverage achieved. If the budget runs out or the deadline hits before these are met, stakeholders must explicitly accept the risk.

Exam scenario and common trap

Question: The project deadline has arrived, but the Exit Criteria state that no High-severity defects can be open. There are 3 High-severity bugs remaining. What happens? The Trap: "The release is automatically cancelled by the QA team." The Correct Answer: QA does not own release decisions. The Test Manager reports the unmet criteria and the associated risks to the business stakeholders, who make the final commercial decision to ship or delay.

Related syllabus sections cover this topic. Reference sections: 5.1.3. See the official ISTQB syllabus for exam scope. Examples are independent; QA-ace is not affiliated with ISTQB.