Test Management study guide

Defect Management Workflow and Lifecycles

A Defect Lifecycle defines the strict sequence of states a bug report transitions through from discovery to resolution. The Test Manager designs this workflow to ensure no defect is lost, ignored, or closed without proper verification.

Practical example

A standard flow: New -> Assigned (to Developer) -> Fixed (Code updated) -> Ready for Test -> Closed (Verified by QA). Alternative paths handle exceptions: Rejected (Not a bug), Deferred (Will fix in a later release), or Reopened (The fix didn't work).

Exam scenario and common trap

Scenario: A developer writes a patch for a critical bug, tests it on their local machine, and changes the Jira status directly to "Closed". The Trap: Candidates see the developer tested it and assume this is efficient Agile practice. The Correct Answer: The team should check its agreed defect workflow and closure criteria. Confirmation testing may be required before closure, but which role can close a defect depends on the organization and the risk.

Related syllabus sections cover this topic. Reference sections: 2.3.1–2.3.2. See the official ISTQB syllabus for exam scope. Examples are independent; QA-ace is not affiliated with ISTQB.