Definition of Ready (DoR) vs Definition of Done (DoD)

In Agile, the Definition of Ready (DoR) is a checklist used to determine if a User Story is clear and testable enough to enter a Sprint. The Definition of Done (DoD) is a checklist used to determine if a User Story meets all quality, testing, and business standards to be released.

Practical example

DoR (The Entry Gate): Does the story have acceptance criteria? Are dependencies resolved? Is it estimated? If no, it stays in the backlog. Prevents "Garbage In." DoD (The Exit Gate): Is the code reviewed? Are automated tests written and passing? Is the feature documented? If no, it is not "Done." Prevents "Garbage Out."

Exam scenario and common trap

Scenario: A User Story's code is written and manually tested, but the automated regression script failed. The sprint ends in 1 hour. The team marks it as "Done" to get points. The Trap: "It works manually, so the user gets value." The Correct Answer: If passing automated tests is in the DoD, the story is NOT done. It does not meet the agreed Definition of Done. How unfinished work and estimates are handled depends on the team’s process.

Additional background: this specific topic is not presented as a dedicated topic in the syllabus. Reference sections: Introduction; CTFL 5.1.3. See the official ISTQB syllabus for exam scope. Examples are independent; QA-ace is not affiliated with ISTQB.